DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations

  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
  • DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations

Project Detail

DC Water and Sewer Authority (DC Water)

dc-water

Project Detail

Project Location: Rock Creek Park
Contract: DC Water Rock Creek Park Sewer Rehabilitations and Combined Sewer Separations
Owner: DC Water
Project Supervisor: Joe McElwee
Contract Value: $12,000,000
Completion Date: January 2012

Description of Work:

Anchor Construction worked with the D.C. Water and Sewer Authority (DC Water) to separate all combined sewer outfalls and upgrade aging infrastructure in areas of Rock Creek Park.

Major work included:

  • Separation of all combined sewer outfalls within the limits of CSO-037, CSO-053, CSO-058 and CSO-051 to insure that no raw sewage can overflow into tributaries
  • Boring under park areas to upgrade aging pipes
  • CIPP lining in multiple locations including wooded areas and through the residential community